Thursday 19 May 2022

Thursday 19th May 2022

John Cooper. Took across 6 bags of sand. Took my drill down but discovered I’d left the main battery on charge at home. Continued breaking up the same rock as Tuesday. Made a little progress before running low on battery power. Then a voice from above turned out to be Wayne out on a run. He volunteered to get his drill so I continued working until I had no power left. Then Wayne returned and lowered his drill. I continued breaking up the same rock, it’s nearly gone now. 2 hours. John.

 

Tuesday 17 May 2022

Tuesday 17th May 2022

John Cooper and Wayne Starsmore. Took across 2 bags of cement and 4 bags of sand together with the refilled water drum. Took my drill down. My plug and feathers used to break up a bit of the rock freeing up 4 sets of Mike’s PFs in the process. Still not quite removed. One mix of cement used building up walls using the debris. Nice draught from the down-dip end. 2½ hours. John.

Sunday 15 May 2022

Sunday 15th May 2022

Cutting up angle beams to help stabilise the loose wall that keeps peeling away. All went well and started building up off the beams. Managed to leave an open space towards Wookey also. 2 mixes used. MK, AT, MH and DM. Mike.

 

Tuesday 10 May 2022

Tuesday 10th May 2022

John Cooper and Andrew Thompson. Two mixes of cement used building up the wall at the Swildon’s end using rocks from the surface. Still not looking safe. 2 hours. John.

Sunday 8 May 2022

Sunday 8th May 2022

John Cooper joined Dave King and Mike Kousiounis for the end of day session. Geoff Newton had already left. Sent a bit of mortar and some rocks down to Mike for walling. 1 hour. John.

Thursday 5 May 2022

Thursday 5th May 2022

John Cooper and Andrew Thompson. Andy at the bottom and John on the surface. Andy started by breaking up the big rock left by Mike and then another one from the side. John hauled the bits to the surface. Then some clatch hauled out. Finally a few rocks broken up for Mike to use as walling material. Depth now 10.8m. 6 bags of sand, 2 bags of cement and 2 containers of water on site. 2 hours. John.