Wednesday, 28 October 2026

Wednesday 28th October 2026

Sam Hill, Oli Hill, Stuart Jellis, Mike Kushy and Alex Randall.

MK headed down with drill around 1730. Once he got to TPC 2 big mixes of cement were made and used building a wall at the top end of the Lower Dig in TPC. The rest of the team showed up together just after 1800. OH, SJ and AR had a go at the Higher Dig whilst SH and MK continued work at the lower dig. SH used the drill to downsize rock, which was then passed up to MK. Smaller spoil was put behind the newly built wall and larger, building type, blocks have been stashed at the bottom of the scaffold. Looking down the passage at Lower Dig a hole has opened up in the floor on the right and the draught increased the more this was cleared. A scaffold bar was braced across the passage and at the end we started building a base to lower the risk of a rock slide. Back in TPC we met the others who looked surprisingly wet and muddy but jovial. Back to the cars for just before 2100. Mike.

Retaining wall (Up dip). Photo MK.

Down dip. Photo MK.

While SH and MK were at the lower dig OH, AR and SJ headed to the higher dig in Tea Party Chamber. Finding a steady drip of water now flowing into the dig we started by enlarging the passage downwards to the low arch of rock seen at the bottom of the dig. In rotations we slowly enlarged this with the sediment slowly becoming wetter and more squalid. OH used the large crowbar to poke at the hole in the base of the dig with the hopes of making it drain away. A lot of loud gurgling noises followed and some of the water drained. After roughly another 30 minutes of digging downwards the hole became blocked and could no longer be found. SJ had one last go at digging in the now very wet dig before we called it a night. Hopefully the water will be able to drain away given time. Still following the right hand wall with a solid ceiling above and the floor continuing to drop away. Oli.

Perhaps also to note that it was possible to hammer the crowbar into the mud at the base of the dig which is slightly to the right of the drain hole. There’s stuff there that could be removed but it’s really restricted and awkward to access. Stuart.

Wednesday, 14 October 2026

Wednesday 14th October 2026

Martin Grass, Mike Kushy, Stuart McManus, Derek Sanderson and Terry Walker. Mainly to show some core members of MCR the cave and get some photos. Got into the cave for 1100 and took the old route in. Once at TPC photos were taken and we cleared several buckets from the scaff dig. We came out the newer route through the boulder rift. Back to the cars for 1330. After a bit of lunch MK went back into the cave and to The Pool Of Tears dig with a drill and 2 batteries. Good progress made and the spoil at the sharp end is now dry and sandy. Another small dam was built with the broken down rock and a good sessions worth of mud tipped into it ready to clear. Out of the cave for 1630. Mike.

P.S. Derek's 83rd birthday next week!!! He seemed to fare better coming out than any of us.

Pool of Tears Dig. Photo MK.

From further away. Photo MK.

Monday, 12 October 2026

Monday 12th October 2026

Mike Kushy and Alessio Sancetta. We met at 1000. Carried some cement across which got transferred into a Daren drum. This and a drill with 3 batteries went in. At TPC AS started down-sizing boulders in Scaff' Dig, whilst MK built more walls in Tea Party Chamber and tried to tidy up as much loose flooring as he could. Periodically we swapped jobs. Really easy access to the side passage going off from the bottom of Scaff' Dig now and there's also quite a big undercut that seems to be leading to a vertical hole. Once the drill ran out we decided to keep clearing as much of the loose stuff  as possible as everything feels fairly safe as it is. Towards the end we decided to have a go at the higher dig in TPC. I personally really like this dig. Towards the end the crowbar was going into the floor with minimal resistance and we were even convinced that some material was dropping down further, although the hole is currently fairly small (but there is a flowstone floor leading to it). We both agreed that it's not worth going down into the initial floor of Scaff' Dig for now but to check the undercut out first. Some cement work could be done but didn't seem entirely necessary, although at the top end of the Scaff' Dig passage there is room for a clever retaining wall and to create some space for backfilling. Back to the cars for 1630. Mike.

Plug & Feather work. Photo MK.

AS coming out. Photo MK.

TPC Higher Dig. Photo MK.

Wednesday, 16 September 2026

Wednesday 16th September 2026

Freya Bearn and Stuart Jelliss. We took a drum of sand in and left it in a plastic bag. The drum and carry bag are back on the surface. The drill and 2 flat batteries are in the lock box. Chain back on the hatch. Quite a few rocks broken and hauled up to the chamber and added to the wall. Stuart.

Friday, 11 September 2026

Friday 11th September 2026

Freya Bearn and Mike Kushy. Mike and I entered the dig by 1pm. We went straight to Tea Party Chamber with two drums of cement, 1 bag of builders sand and a drill. I went through the squeeze at the bottom of the dig and shuffled to the bottom, following the ceiling down, where it got considerably tighter and there was a crystal pool in front of me. On the way back up, I was intrigued by a phreatic tube down to the right. I then squeezed back out. About five minutes later, a large boulder collapsed at the entrance to the squeeze, blocking it in and causing various other boulders at the top of the crawl to collapse in its wake. We exchanged worried glances - how would I (or anyone else down there) have got out? Having decided it was too nauseating to keep thinking about it, we got to work downsizing some of the collapsed boulders with plug and feathers, which I then hauled up using a bucket. We cleared out the hole at the bottom of the dig, which is now much bigger. Once Mike had explained the ratios for cement mix, I mixed up three batches which I lowered one by one. Mike then used these to cement up the wall on the right hand side. We checked the time and, much like Lewis Carroll’s white rabbit, exclaimed that we were late, and swiftly left, as it was already 5 pm. The dig already feels a bit safer, but it is definitely one to be approached with caution.

1 empty drum and a few empty bags brought out. 2 full drums of cement in cave, just need to take some dust in next, no cement left in the lockbox. Freya.

Freya at work. Photo MK.

Bottom of dig. Photo MK.

Friday, 4 September 2026

Friday 4th September 2026

Ed Ford and Mike Kushy. We met for 15.45 and headed in with a heavy bag of stone dust each. Many mixes made (used 2 full drums of cement and relevant sand). There's now a bright green scoop in TPC to help gauge mixes better. The nut on the pulley hanger has now been tightened. Good amount built but didn't quite make it all the way round, it would be nice to get this finished Sunday to allow a safer clearance session mid week. There was hardly a draught to begin with, around 7pm it really picked up. Back to the cars for 2030. Half a bag of cement in the lockbox, which should restock the 2 drums brought out. Mike.

Wednesday, 2 September 2026

Wednesday 2nd September 2026

Oli Hill and Sam Hill

Met at half 5 and made quick progress down to the dig.
A bolt and hanger was installed high up on wall for hauling (bolt needs a spanner to tighten it up and a pulley adding).
20 buckets of loose stuff was hauled up and then numerous large boulders were broken up. Hole into bedding tube has been opened up again and a good draft was felt towards the end of the session. Left with lots more rocks to break down and lots of loose stuff but a cementing session is definitely needed before any more downwards progress. Larger voids opening up in the floor with lots of calcite and water worn boulders coming out.
Out by half 8.30hrs. Sam.

Installing pulley. Photo SH.

Looking down. Photo SH.

Large calcite lump pulled out. Photo SH.

Monday, 31 August 2026

Monday 31st August 2026

Oli Hill, Sam Hill, Mike Kushy and Mysti Ommer. We all met at 1100 and carried 2 bags of dust in each, apart from one person who had the drill and a bag of sand. OH and MO went through to MHH and brought a length of rope back with them. This was used on a bucket for hauling (ideal time to get a pulley installed). SH meanwhile set to breaking up rock in Scaff' Dig with PF's. After we spectated SH for a while,we decided to have a go at the 'Top Dig' in TPC. Easy digging and OH/MO took turns at the front. A 3rd person wasn't really needed so MK went to assist SH. Towards the end we were mainly clearing clatch, with still loads more to clear. Before we left some hefty boulders were moved from the floor at the end. Interesting holes in the floor appearing now and boulders still getting larger. Another interesting thing was that all the boulders we broke up today weren't actually limestone, all rotten inert calcite type material which PF's didn't work great on (none of these boulders were smaller than a microwave!), almost as if this area was one big calcited plug. We had a chat today and agreed all building work should be done on a weekend as we keep losing bits of wall where enough time isn't being spent on construction. All out for 1530. Mike.

Top Dig was mostly mud and some soft rocks, with OH and MO taking turns to break it up and empty buckets into nearby spoil. After a couple of hours, a significant amount of the floor area had been removed and lowered, but still plenty of work to be done removing sediment, with an intriguing undercut down towards the back right. Mysti.

Wednesday, 19 August 2026

Wednesday 19th August 2026

Sam Hill, Mike Kushy and Michael Waterworth.

MK and MW met for 1800 and took 2 drums of cement in. At TPC we met SH who had been down for a while splitting up boulders from the scaffold dig. We all cleared the loose spoil to the main chamber. Some work was done adding extra bars and removing the higher diagonal brace that goes across the middle so we can now add a pulley system. SH had to leave at 2000, so the other pair set to building some walling. 2&1/2 drums of cement in cave and a fair amount of building sand, just need dust. Several huge boulders to break up at the bottom of the scaff dig next time. Really good draught coming out today. MK and MW got to the cars for 2100. Mike K.

Scaffold Dig. Photo SH.

Tuesday, 4 August 2026

Tuesday 4th August 2026

We met for 5pm at the dig, ready with a bag of cement. We were underground for half past. At Boulder Rift Chamber we grabbed all but one of the bags of sand/dust. With minimal spillage five bags and ourselves dropped down into Tea Party Chamber. Having had a good look around making a plan we set about it, 3 mixes were made up whilst I cleaned out the bottom ready for walling. The un-cemented side was walled up and a small step added. The second load went under one of the large boulders to support the wall ready for downwards progress next time. 3.5hrs 

We emptied all the bags in TPC, bringing all the bags out! 4 broken tackle bags were taken from site & washed, in the hope that they can be fixed. There is no cement, but 3 bags of dust and 2 bags of sand left in Tea Party Chamber.
Sam Hill.


Looking down. Photo SH.

Looking down. Photo SH.

Saturday, 18 July 2026

Saturday 18th July 2026

Freya Bearn, Joe Biddie, Sam Easton, Sam Hill, Michael Kousiounis, Leila Nicholson and Mysti Ommer. 

We met for just after 10.00 and lowered 6 bags of sand/dust and a drill bag. The drill bag went down to POT and the other bags got taken through to the Boulder Rift chamber. SE, MK and MO went to the Tooth Dig end. Whilst there we sent the older spoil lower down as well. FB did the awkward spot and those at the dig face took turns clearing mainly mud. Around 12.00 MO and SE had to leave. SH took over from FB and clearing resumed but at a slower pace. Around 13.00 SH, JB and LN went to see TPC taking 3 scaffold bars with them. FB and MK got the drill out and, with MK mostly spectating, FB broke up the last and largest boulder with PFs. SH returned after some time, JB and LN left. FB, SH and MK then took turns poking and scraping at the sediment bank wall at the sharp end. It became apparent there was a strong icy draught coming out of a 1 inch x 1m gap above the sediment leading to a heavily calcited rock blockage ahead. The crowbar pushes through the whole way in places, but alas no black voids. Out for 15.00. Mike.

Sunday, 5 July 2026

Wednesday, 1 July 2026

Wednesday 1st July 2026

Mike Kushy and Mike Wise. Met at 17.00 and got underground for 17.30 after lowering 7 bags of materials, 4 swivel clips and a drill bag. All of this was taken through to TPC. MK started preparing mixes whilst MW cleaned areas in the pit and built up the left hand wall (as you look at the solid wall), 3 mixes in total. MK in the meantime was using pfs to break down larger rock for more decent building blocks. Another horizontal added to strengthen the frame. 2 sand, 3 dust and 2 cement left in cave I believe (enough for another few mixes). Out for 21.30. Mike K.

Saturday, 27 June 2026

Saturday 27th June 2026

Mike Kousiounis (Kushy) and Alessio Sancetta. Met at 10.00 and packed 7 bags of various materials which we got down into the cave, plus an extra bag with drill, around 10.30. We left the drill at POT and carried the remaining 7 bags through to TPC. 5 mixes made. There are now 2 bags of dust left in cave, no sand or cement. AS went through to MHH to get water and reported the tub is full and likely to fill again by tomorrow. We took 3 bags of bags out of TPC and headed back to POT. After a quick lesson in pf AS quickly dismantled all the large boulders, leaving only 1 behind. Great draught as usual and very cold for anyone not working. Out for 1630. Mike.

Allessio at Pool of Tears. Photo MK.

Friday, 26 June 2026

Friday 26th June 2026

Mike Kushy, solo with John Cooper as callout. Headed down cave around 17.30 with 4 full length bars, 2 shorter ones and a sack with drill and some clips in. At the Boulder Rift chamber the longer bars were left and exchanged for the two bags of dust left on Wednesday. Got to TPC and did 3 mixes. 2 drums of sand , no cement and no water...although I did check the collector in MHH and that is full. Took out 2 bags of bags and drill. In the Boulder Rift chamber a stone was chocked into the boulder with the big crack and marked for measuring. Out for 21.30. Mike.

Cracked Boulder in Boulder Rift. Photo MK.

Marker. Photo MK.

Wednesday, 24 June 2026

Wednesday 24th June 2026

Freya Bearn, Mike Kushy and James Vickery. We all headed to POT around 3pm with 2 bags of dust (left at connection to Boulder Rift) and a drill. MK went to the Tooth Dig end to clear, with FB on the rope in the awkward chamber and JV filling buckets. Once the dam was cleared we assessed the front and FB felt confident enough to go first. The whole ceiling looked to be shattered and needed crowbar work. FB managed some and then JV went to the front and removed even more. We cleared back to the dam and after a while MK went to the front. Huge boulders stacked randomly which we tried to move back and created another dam (supports) with. PF or capping work needed next to downsize some more boulders. Have no idea where all the spoil will go so maybe we keep the blocks larger and cement them into tactical places?! The view ahead is of a solid bedded ceiling with no fractures at all and a mud filled trench down the right with a nice hole which can't quite be got to safely yet. 3 hours. Mike.

Before clearing. Photo MK.

Partially cleared. Photo MK.

End of session. Photo MK.

End of session. Photo MK.

Saturday, 20 June 2026

Saturday 20th June 2026

Freya Bearn and Mike Kushy.

Tea Party Chamber Dig.

We got down the cave for 1100, after lowering 3 bags, 1 drill box and 5l of water which we carried through. We also picked up another 3 bags on route from The Boulder Rift chamber and took everything to TPC. Once we got to TPC FB started mixing and MK started cleaning rock ready for cementing. MK gave FB a quick lesson in PF work and she downsized boulders whilst MK cemented. 3 mixes in total today. At one point a huge boulder came out from the right hand side (as you face the solid wall) and nearly took MK's leg out, so MK added another vertical on that side and braced it off another corner with a diagonal. 1 bag of grit sand, 1 bag of builders, 2 drums of cement, 1 scaffold bar and 2 x 5l of water in cave. We headed out with 2 bags stuffed with bags, the drill box and we also picked up a redundant 50m of firing cable on the way to Puddle Dig (Pool of Tears).

Scaffold dig. Photo MK.

Puddle Dig.

Here we cleared back to the dam until it was full, then we drilled 5 holes @ 600mm x 10mm. Noise made. Out for 1600. 2 whole bags of grit sand in lockbox, no cement. Mike

The sharp end at POT. Photo MK.

Wednesday, 17 June 2026

Wednesday 17th June 2026

Puddle Dig Team: Freya Bearn, Sam Hill, Stuart Jelliss, Mike Kushy and James Vickery.

Four of us arrived at the entrance at about 18.30 and headed down to Puddle Dig. We carried in 5 bags. 1 of which was sand taken on to TPC by MWa, the other 4 had 3 sand and 1 cement. These were left in Boulder Rift Chamber for use in the TPC dig. Initially James and I were clipping buckets of loose rocks from the dam onto a rope which Mike and Sam then hauled up. However when Stuart Jelliss arrived I was sent down to the dig face. At the bottom of a slope lay an uninviting crawl into a pool of mud and loose bits of rock, which terminated where a large boulder sloped down into a puddle of sloppy mud.

After a while of clearing the larger chunks of rock from the foot of the slope, which I handed up in buckets to Stuart, I ventured towards the far end of the crawl to the foot of the boulder which sloped down from the ceiling. I began to clear the mud by hand, expecting to hit solid rock beneath it, but was instead met by a gritty sand-like substance. Beneath me was a large slab of rock which prevented me from going too far forwards, but I managed to loosen much of the grit with a crowbar which I continued to shovel out. To my excitement, when I pushed the crowbar into the grit, it kept pushing forwards without hitting an endpoint. Furthermore, having cleared enough mud out of the way, I could put my hand underneath the boulder and felt that it arched upwards. It seemed as though beyond the grit and mud was a large gap leading downwards, which could be made accessible by widening the gap between the boulder which sloped down and the rock on the ground. By the time we had stopped, enough had been removed that I could no longer reach through with my arms.

Mike and Sam came down to look. Looking behind us on the way out, we could see cracks in the ceiling beneath which I had been digging. Mike and Sam debated putting in scaffold bars, but it was agreed that the ceiling would have to come down to make it safe. This would also give a bit more room for manoeuvre, as currently there is not space to sit up. Out by 21.00. Freya.


Tea Party Chamber Dig Team: Mikey Waterworth and Mike Wise.

Dropped into the entrance just after 1730 with a drill and grinder in a tackle bag, two batteries in a small box and 3 x 25 litre containers 2 of which were cut as buckets and 1 as a drag tray. After some discussion at the TPC dig, including Mikey disappearing some distance into the floor, operations commenced. All references are made from the viewpoint of someone standing immediately above/in front of the dig.

4 mixes of cement were made and used to fix rocks in place in the large gap below the two large boulders at upper left.

A second horizontal bar was fixed across the front between the two uprights and wedged at each end against rock - see first photo below.

Mud, small rock and some quite large rocks were removed from the floor of the dig in the centre and right hand side. The small stuff was placed above the dig on the left to form a flattish platform and otherwise used to fill voids in the main boulder slope

Large rocks including those from the dig were placed against the new upper horizontal bar as part of our plan to build this up stage by stage to level out the main boulder slope - see video.

The cement mixes used up all the available water, all the cement except for 3/4 of one large daren drum and all the sand except for 1 bag.

We agreed that placement of two bars, one either side between the the two uprights and the two lower bars running to the hanging bedding wall (see photo 2) would be needed to further stabilise things. Also the mud and stone wall adjacent to the bedding wall on the right needs stabilising which could be done by adding more bars with pieces of GRP grid behind and stone wedged in any remaining gaps.

Before leaving we had a bit of a tidy up putting all scaffolding bits up with the red tackle bag and gathering what sand we could find into one location. We left some of the cut 25L positioned as drip collectors but in these weather conditions they are not going to collect very much.

Mikey took the drill/grinder bag up but the battery box and 3 empty daren drums were ferried one at a time by rope up the light connection. The daren drums were chained up through the more tricky parts of the exit although one did escape our care on two occasions.

In the Boulder Rift connection we found 4 tackle bags stashed. Apparently they were 1 of cement and 3 of sand.

We reached the surface hot and bothered but satisfied at 2115.

Mike Wise

Dig location. Photo MWa.

Closer view. Photo MWa.

Dig. Video MWa.

Saturday, 13 June 2026

Saturday 13th June 2026

David Cooke (Cookie) and Mike Kushy. We took the 4 scaffold bars by the entrance shaft down to TPC. DC's first time in the cave, so he went through to see MHH. MK started making a mix and this was used up building up to support a corner area. DC returned and continued with another 2 mixes, whilst MK built and added another vertical pole. It's all feeling a lot safer already and we even braved venturing below. There's some hefty calcited boulders to build off lower down and the job isn't looking so difficult to me anymore. 4x drums of sand, 2x cement and a small amount of dust in cave, need water also. We came out the old route. 3 hours. Mike.

Friday, 12 June 2026

Friday 12th June 2026

'Caucus Race'...?!

Harley Bennet, Ed Ford and Mike Kushy. Got to the entrance for just after 1700. We lowered 5 heavy bags containing sand, cement and drill and also picked up the scaffold clip bag on route. We leap frogged and ferried them down to TPC. MK and HB had a go at the higher end dig in TPC whilst EF down-sized and moved larger rocks from in and around the scaffold dig with PF's. After a while MK joined EF and the pair worked on cementing whilst HB spent his time building walls at the higher dig. More rock removed and we now have a square frame. Lost track of how much material is in cave but we brought out all the tackle sacks and these are in the lock-box on surface along with 1@1/2bags of sand and 2/3 bag of cement. MK and HB popped to get tools from MHH and the air felt very stale, whereas there was a lovely cool breeze coming up the light connection today. EF placed a section of small ladder he acquired (thanks Mick) into a gap in the ceiling right where you get into the thrutch. I personally really liked it, just needs securing. Out for 21.30. Mike.

There is/was caveable space down there. Photo MK.

MK in 'Scaff' dig. Photo EF.

The 'Higher' dig. Photo HB.

Left wall. Photo HB.

Right. Photo HB.