Mike Kushy, Trevor Hughes and John Cooper.
Just MK to start with, filling up the retaining wall built yesterday, quite surprised how set the cement was already. Started breaking up some rocks then TH Showed up. TH in the bottom pit filling up small buckets, with MK at the top lifting buckets on rope. Every 4 small buckets MK ferried up cave to the higher up rift, at least a dozen loads of 4 done. TH broke up some decent sized rocks. TH had to leave so MK went down to use up the rest of the drill batteries. TH left taking 4 small buckets out with him. Drill batteries spent MK made his way out with drill looking forward to a rest and a tea at Upper Pitts. MK arrived on surface to find JC mid mix. After a short break MK then went back down cave and ferried 3 big buckets of cement to the bottom. This was used building up more retaining wall and supporting more underneath the climb down wall. 5 hours. MK.
Bottom of pit after clearing. Rock my right foot is on has now been moved. Photo MK. |
View underneath the rock moved in first photo. Photo MK. |
No comments:
Post a Comment