Wednesday, 6 November 2024

Wednesday 6th November 2024

Mike Kushy and Mike Wise. MK to start with, filling up bags and moving rocks. A lot of spoil has gone ahead and is unreachable. MW arrived just as the bags were full. These were moved up to the connection  then with MW in the stacking chamber everything was cleared. 4 holes drilled and set. All went off well. 3 hours for me. MK.

Tuesday, 5 November 2024

Tuesday 5th November 2024

Mike Kushy, Sam Hill and Alex Randall.

MK to start with, filled up bags and moved rocks up cave. Hammer and chiseled for a while. AR and SH arrived and moved the spoil to the stacking chamber. 4 holes drilled  2@750 and 2@600. Good holes. All went off well. 3 hours for me. MK 

Spoil. Photo MK.