Mike Kushy, Hollie London, Ed Ford and Mike Wise. MK and HL to begin with. We made our way in around 5.30pm with batteries and a tub of sand. Picking up 2x scaff' bars on the way everything was taken to TPC. EF arrived not long after with his Dewalt 18v drill so we handed him some pfs and he opened up the head of the light connection more. This has revealed that some extra stabilisation needs doing here, possibly some cementing and a scaff' bar for a brace. Meanwhile HL was attacking The Hookah Pipe with the sds and chisels, whilst MK did more furnishing of TPC's floor. MK then went through The Hookah Pipe and used the Bosch sds from the far side. MW arrived and made it into TPC for the first time and said it wasn't as bad as we made out. He brought his Makita 36v in and attacked the pipe from TPC side. We all swapped turns tidying the floor and chiselling. Towards the end EF managed to get through THP into the decorated chamber beyond so he did some pf work from the far side. HL had a go at THP too. I think she could have done it but the squeeze is very intimidating and it's not going anywhere. Probably another session and we may be able to start hauling buckets of mud back into TPC. 3 tubs of sand and 1 tub of cement in cave, no water. There is 5l bottle of drinking water on the shelf near the bottom of the shaft. This will need an empty tackle sack to take further in. We also need to take in a heavier lump hammer for calcite. 3 1/2 hours. Mike K.