John Cooper and Mike Wise. MW charged the 4 holes drilled by JC yesterday. JC advised some of them might be longer than expected, so with only 2m of 40g, we prioritised the two holes on the left and the upcave hole on the right and packed them to the brim. The remaining 250mm or so of 40g went into the 4th hole. JC kindly took the bang bag out while MW connected the det and brought the cable back out to the surface. Fired satisfactorily. MW bang wire remains in place. 1.5 hours. Electrical tape was used in the top of the first hole, but subsequently, 4" cable ties were used because the slimy, wet conditions stopped the tape sticking. Mike.