Monday 18 April 2022

Monday 18th April 2022

John Cooper, Mike Kousiounis and Andrew Thompson. When we arrived the winch setup was a real mess. We reset it up and later watched as one of the sheep had another go at demolishing it. The sheep went under a scaffold leg and lifted it up as a means of scratching its back. With no weight on it they were able to move the legs several metres rotating the winch itself at the same time! With Andy and Mike at the bottom a steady stream of debris, rocks and clatch, came out. A half hour lunch break was an opportunity to take one of Mike’s batteries back for recharging. Continued after lunch using my batteries before finally going to get the newly charged one to finish off the day. One mix of cement done in the morning session and a second mix in the afternoon one. Depth now 10.2m. 5 hours of work. John.

 