Sunday 23 June 2024

Sunday 23rd June 2024

Mike Kushy, solo. Started with breaking up some rocks at the sharp end. Also took in some sacks to fill up with clatch. Went to surface and made a mix with 1 bag of sand. This was put into 2 buckets and taken down to build up a supporting wall at the sharp end. A lot of clatvh from the floor was put behind the wall. Should be safe to break up the 2 rocks ahead next visit. Tried to squeeze down the right hand side and got my hips to an edge, my legs couldn't touch a floor so being alone I gave up. Not that tight tbf. Finished the session by clearing back some rock to the small chamber. A bit of rock still at the bottom to clear. Good draught. 5 hours.

MK's YouTube video from today

The squeeze I attempted to the right hand side. Photo MK.

The current sharp end. Photo MK.

Saturday 15 June 2024

Saturday 15th June 2024

John Cooper, Pete Hann and Kate Lawrence. One mix of cement taken in, two loads, and used by Pete continuing with the left-hand wall, then the right-hand wall, in the Boulder Chamber. Once the cement was with Pete, John and Kate visited the current dig face. They then went on a tour of the old cave. From the bottom of The Pit we could hear Pete shifting rocks about. We then went into the Upper Bedding Chamber, down through the Calcite Squeeze into the Lower Bedding Chamber and down to the bottom of the Cement Dig – very gooey. Back up and into Boulder Rift. We ignored the lower parts and made our way to the top and exited via the squeezes dropping down into the current dig. Pete was just finishing up the cement so we came out for tea and cake. There is room behind Pete's walls to put a load of clatch when it's brought up from the current dig. 1½ hours. John.

Wednesday 12 June 2024

Wednesday 12th June 2024

John Cooper. Afternoon. One mix of cement taken in, two loads, and used continuing with the left hand wall in the Boulder Chamber. 2 hours. John.

Wednesday 5 June 2024

Wednesday 5th June 2024

Afternoon. John Cooper and Mike Kousiounis. John surveyed around Boulder Chamber and down to the current dig face where Kushy was breaking up boulders. Then went and did a mix of cement. One load used on the right at the bottom of the drop below the shelf and the other on the left in Boulder Chamber extending Pete Hann’s wall. 3 hours. John.

Evening. Oli Hill, Sam Hill and Mike Kousiounis. Oli and Sam started by hauling rock from the dig face up to base of climb and breaking up the oversized stuff. Then joined by Kushy who helped move the rock up to Boulder Chamber. Kushy then went around to the other side, Boulder Rift, and Oli and he then both did the connection.  Whilst Oli was being shown the rest of the cave I started on the next big boulder at the dig face. Kushy left and Oli helped me until drill battery was used up. 2.5hrs. Sam.

The way on down. Lots more boulders to remove. Photo SH.

Looking under the shelf on the right on the picture above. Photo SH.

Looking down towards the end, way on is to the right. Photo SH.

Friday 31 May 2024

Friday 31st May 2024

Mike Kushy, solo. Removed the boulder that was cemented around last time. Managed to squeeze through ahead and gain a few metres, wide bedding and a side rift going off to the right. After this I decided to tickle the roof and collapsed some boulders, losing the few metres gained. These rocks were then attacked until the batteries were spent. All the rocks move and can be broken down safely. Plenty of rock at the bottom to clear. 5 hours. MK 

Side rift heading into the cliff wall. Photo MK,

Bedding view ahead. Photo MK.

Current dig face. Photo MK.

Wednesday 29 May 2024

Wednesday 29th May 2024

John Cooper and Andy Thompson. Started by hauling out the rocks left at the bottom of the entrance shaft. Then moved down a stage and moved the rocks left at the bedding up to the bottom of the entrance shaft. Then moved on down again and moved all the rocks off the shelf across to the slope. Then moved down to the very bottom and cleared the rocks from there into the chamber where I suggest they are used as walling (cementing required). Then moved back up cave and moved the rocks from the slope up to the bedding. With all stacking spaces now full we repeated the clearance of the base of the entrance shaft but this time ferried the rocks from the bedding to the bottom of the entrance shaft as space became available. Only one rock would not fit and required the use of an open topped hauling bucket. 2½ hours.John.

Sunday 19 May 2024

Sunday 19th May 2024

Mike Kushy, Sam Hill and John Cooper.

MK solo to start with, set about plug and feathering work on the boulder ahead. SH arrived not too long after. We then moved rocks from the bottom up the 10ft climb. SH continued ferrying rocks up cave whilst MK used up the rest of the batteries on the first drill. SH then took over drilling work and MK ferried rocks up the 10ft climb and further up cave. MK came back down and when SH had used up his drill the pair swapped again and MK used up the final drill batteries and just managed to split any loose rock available at the dig face. Meanwhile SH cleared rocks back again and headed for the surface to see if JC had arrived to mix the cement. He was, so 3 buckets of muck were brought in by SH. 1 bucket used on the shattered boulder higher up, as new cracks have been appearing. The other 2 were used at the dig face to stabilise higher rocks, ready to remove one rock that is impeding progress on. A nice trench has appeared in the floor, cutting across the passage and heading into the cliff face. This leads to a small hole a couple of metres in which swallows up alot of spoil and draughts well. Plenty of rock at the bottom of the shaft to come out and various piles throughout the route to the dig. 6 hours for me. Mike.

MK's YouTube video from today

Sam Hill plug and feathering at the dig face early on. Photo MK.

Large beetle. Photo MK.

Dig face after clearing and cement work.
Trench, where my foot is, is heading under the undercut. Photo MK.

Wednesday 15 May 2024

Wednesday 15th May 2024

John Cooper and Sam Hill. Sam arrived first and started moving Andy’s rocks upwards, including downsizing some to a manageable size. When John arrived work continued moving rocks on up to the bottom of the entrance shaft. When most were there John went to the surface and hauled 27 loads of mainly single rocks, but 5 loads had two smaller ones in the bucket. Once all had been cleared Sam went to the bottom to start plug and feather work on the end slab. Rather than just watch John said he’d go into the old cave and see if he could see or hear anything of Sam. From the bottom of the Pit Sam and John could talk to each other but there was no light connection. Sam had the impression John was below and to the right, which John agreed with. John then continued on into the Boulder Rift and climbed up to the top where he was able to see Sam’s light and guide him through. Sam then completed the first round trip Finally he continued with more plug and feather work to use up the power in the drill batteries. Now need to go and add details to the survey! 2½ hours for me.An hour longer for Sam. John.

Saturday 11 May 2024

Saturday 11th May 2024

Sam Hill. Solo trip down downsizing the end slabs. First one broken up revealed a hole going down following the bedding. Started chipping away at the other boulder until drill battery was used up. 2.5hrs. Sam.

Start of session. Photo SH.



Hole off under right side. Photo SH.

Wednesday 8 May 2024

Wednesday 8th May 2024

John Cooper and Andy Thompson. Whilst Andy had a look at the dig face John moved the rocks that were left in the Chamber up one stage before moving on down. With Andy loading at the bottom of the 3m climb and John hauling we spent about 90 minutes moving rocks out. Four that were too large for John to haul were left. There are also bits left here and there. John then continued on moving the rocks that he’d moved earlier on up before finally arriving at the bottom of the entrance shaft with them. Andy was following on behind with the rocks we had hauled up the climb. Some of these got as far as the slope above the shelf whilst others were left on the shelf. Finally, Andy hauled John’s rocks to the surface, 15 loads. 3 very sweaty hours. John.

Sunday 5 May 2024

Sunday 5th May 2024

Mike Kushy, Adrian Miles, Jack Miles and John Cooper.

MK started just after 9.30, took in 2 drills and set to work on the slab ahead. At some point AM and JM arrived and cleared the rocks at the base of the shaft to surface. Around 12.30 they joined MK at the bottom. With MK handing up the 10ft to AM, then back to JM in the chamber most of the bottom was cleared. AM then came in to see the end before they departed. The rest of the drill battery was used not long after. A hole below the slab has appeared and draughts really well. The bottom is filled up with rock, which needs clearing now. The chamber also has a lot of loose rock in it. Around 2ish MK got to surface and caught JC getting a mix on. This was used stabilising some more of the floor in the chamber. All stone dust now used up. Some of the bungees have snapped on the surface shelter, also the bucket deviation is very worn and could do with replacing. 5 hours, Mike.

MK's YouTube video from today

The current end. Photo MK.

Friday 3 May 2024

Friday 3rd May 2024

Alex Hannam and Sam Hill. Good session breaking up the slab. Started solo, then briefly joined by Alex H to help haul half the rock up to the chamber. Alex then left and I continued breaking the boulder up until I ran out of drill battery. 2hrs. Sam.

Boulder at start of session. Photo SH.

Boulder at end of session. Photo SH.

Wednesday 1 May 2024

Wednesday 1st May 2024

Alex Hannam and Sam Hill. Opened up climb down a little but drill bit was very blunt. All rocks then hauled up to the base of shaft. All now ready for the next slab to be broken up. 2 hours. SH.

Saturday 27 April 2024

Saturday 27th April 2024

Mike Kushy, solo. Took in drills and broke up the rest of the 1st section of slab. This is now in pieces at the bottom and ready to be cleared. Started 4 holes on the next slab. Should be much easier going on the next piece. Nice draught from below. Went to surface and made a mix to fit into 2 buckets. Took the mix and used it stabilise around the 10ft climb. This should now be safe to straighten out. 4 hours, MK.

Current dig face, red line shows the line of drill holes started. Photo MK.

Wednesday 24 April 2024

Wednesday 24th April 2024

John Cooper, Alex Hannam, Sam Hill, Callum Simmonds and Andy Thompson. Andy worked on the surface, initially clearing the rocks John stacked by the entrance on 14th April and then hauling. Sam took his drill in for p/f work and John took in one of the large hauling buckets with a tape handle. Initially Sam was at the bottom loading rocks into the large bucket which Callum hauled up the 10ft climb and passed them to John to stack in the Boulder Chamber. Once that was done Callum went down for a look and John made a start moving the rocks outwards. Some of the larger ones were broken up by Sam. Alex arrived and also went for a look at the bottom. From then on rocks were moved up in stages to the shelf and then on upwards before eventually reaching the bottom of the entrance shaft. Callum had to leave to go to work but the rest cleared all the rocks to the surface. The slab is now ready for Kushy’s attention. 2 hours.