John Cooper and Andy Thompson went across early afternoon and
assisted Kushy, Mark Helmore and Al Mills for a bit of rock hauling. Tuska had
already left. Empty water container brought back to Upper Pitts for refilling.
1 hour. John.
To watch the diggers in action on YouTube click here
Sunday, 13 March 2022
Sunday 13th March 2022
Sunday, 6 March 2022
Sunday 6th March 2022
Mike, Tuska, Chris W. and John. Mike and Tuska breaking up boulders and winching out for a few hours, about 6ft lower again. Bedding type roof heading towards Wookey direction at about 45°, the opposite way there is a draughting hole in the floor. Cement work done at the end with Chris and John popped over to say “Hello”. Mike.
Friday, 4 March 2022
Friday 4th March 2022
John Cooper and Dave Morrison. Some clatch moved to surface so
Kushy can Plug and Feather more boulders. 1 hour. John.
Saturday, 12 February 2022
Saturday 12th February 2022
Wednesday, 2 February 2022
Wednesday 2nd February 2022
John Cooper and David Morrison (Tuska). Tuska organised delivery
of the winch and ladder which he started fettling in the morning. I turned up
about 1.30pm with some water as there was none for mixing cement. Spent a while
deciding where and how to fix the entrance ladder. Left it propped on rocks
pending a proper base being constructed Sunday. Finally spent some time cutting
off welded on nuts from the winch frame. 2 hours for me. John.