John Cooper and Trevor Hughes. John in at 18.00 to add a bit to
the survey of Boulder Rift. Came out 19.00 to meet Trevor then both in to bang
yesterday’s holes. All went OK. Wire left just below lid. 2 hours for me. John.
A good firing- as per your picture. Maybe not a breakthrough but certainly a vast pile of rocks to clear. A lot of small(ish) rocks ahead, a good stacking/removal policy is needed. Having said that it does, indeed, look very promising. Trevor.
To watch the diggers in action on YouTube click here
Wednesday, 4 September 2024
Wednesday 4th September 2024
Tuesday, 3 September 2024
Tuesday 3rd September 2024
John Cooper. Drilled holes ready for banging. 2 in first
boulder (vertical) and 1 in second boulder (horizontal). 1 hour. John.
Holes drilled 12mm top 100mm then 10mm: red 500mm deep, blue 300mm deep.
Red vertically downwards, blue horizontal.
Red boulder is only about 300mm thick.