Thursday, 29 August 2024

Thursday 29th August 2024

Mike Kushy. Went in at 4pm. Retrieved bang wire and stated clearing debris. Bit fumey in the boulder chamber, but below this the air was okay. Bang did just as needed. Cleared back as much as possible and broke up the easy to pick rock. Lots of cement work to be done before attacking the next boulder ahead. A view beyond this boulder shows the floor dropping away more steeply. A cross section where fault and bedding passage meet ahead and what looks to be a significant hole at the bottom. Draught present, but not obvious. 3 hours. MK

MK's YouTube video from today

Bang debris. Photo MK.

After clearing. Photo MK.

Wednesday, 28 August 2024

Wednesday 28th August 2024

John Cooper and Trevor Hughes. John arrived at 18.00 and went to in to deepen the holes already drilled. Did the two on the right and the one in the floor but didn’t touch the ones on the left. Brought drill out and Trevor arrived about 19.00. Charge set up but holes not cooperating as wished for. Out by 20.00 leaving reel at top of ladder to be removed next time. 2 hours for me. John.

There are now 3 bags of sand, 2 of dust and a new bag of cement on site. Plus 25L water container topped up.