Sunday, 10 March 2024

Sunday 10th March 2024

Mike Kushy, Trevor Hughes and John Cooper.

Just MK to start with, filling up the retaining wall built yesterday, quite surprised how set the cement was already. Started breaking up some rocks then TH Showed up. TH in the bottom pit filling up small buckets, with MK at the top lifting buckets on rope. Every 4 small buckets MK ferried up cave to the higher up rift, at least a dozen loads of 4 done. TH broke up some decent sized rocks. TH had to leave so MK went down to use up the rest of the drill batteries. TH left taking 4 small buckets out with him. Drill batteries spent MK made his way out with drill looking forward to a rest and a tea at Upper Pitts. MK arrived on surface to find JC mid mix. After a short break MK then went back down cave and ferried 3 big buckets of cement to the bottom. This was used building up more retaining wall and supporting more underneath the climb down wall. 5 hours. MK.

Bottom of pit after clearing. Rock my right foot is on has now been moved. Photo MK.

View underneath the rock moved in first photo. Photo MK.

John Cooper. I thought all I was doing today was loaning my drill to Mike to use but during lunch in the Hunters',  post my Swildon's Hole trip, I was approached by Trevor saying Mike was expecting me to do a cement mix. Finished lunch then went across and was just preparing to add the water when Mike emerged. I think he regretted asking for the mix but it was too late so after I'd finished the mix, split into 3 loads as usual, he descended to use it up. I cleared up and packed things away then went back to Upper Pitts for afternoon cups of tea. There is 1 bag of sand, no cement but plenty of stone dust still on site. 1 hour. John.

Saturday, 9 March 2024

Saturday 9th March 2024

Mike Kushy, Pete Hann, Adrian Vanderplank, John Cooper and Nigel Graham.

MK started at 10 and got about down sizing the stacked up boulders left from mid week. All broken up and stacked higher up then the rest turned up. With NG on surface all the rocks were cleared. After this PH went to the sharp end and many buckets of clatch were sent to surface. Some big boulders removed from the floor and walls by AV capping. PH set about cementing the climb down and some rocks in front, a small retaining area ready to be filled in. Whilst this happened MK and JC did a little clearing within the rest of the cave. Interesting voids lower down, one which looks like a significant inlet coming directly into the solid wall. 5 hours for me. MK

MK's YouTube Video from today

Pete at the deepest point of the dig. Photo MK.

Pete on his way out, pit below. Photo MK.

Straight ahead from the top of the pit. Photo MK.

Passage over the top,which we aim to keep open for future exploring if needs be. Photo MK.