John Cooper and Andrew Thompson. Started by hauling clatch out.
Then a bit of boulder breaking to create walling material for 2 mixes of
cement. During the hauling of clatch a boulder was dislodged from somewhere in
the shaft which fell hitting John’s helmet and left shoulder. A bruise is now
developing from the rock which was about the size of 2 house bricks. Later on
the empty bucket came down on its own! I really don’t trust the hook on the
hauling rope, needs to be a closed one so it cannot fall off accidentally.
Depth was 10.4m to foot level. 2½ hours. John.
To watch the diggers in action on YouTube click here
Tuesday, 26 April 2022
Tuesday 26th April 2022
Wednesday, 20 April 2022
Wednesday 20th April 2022
John Cooper, Mark Helmore and Andrew Thompson. Started by hauling
clatch out. Then 1 mix of cement and a bit of boulder breaking, just hammer.
Depth was 10.4m to foot level. 2 hours. John.
Monday, 18 April 2022
Monday 18th April 2022
John Cooper, Mike Kousiounis and Andrew Thompson. When we arrived
the winch setup was a real mess. We reset it up and later watched as one of the
sheep had another go at demolishing it. The sheep went under a scaffold leg and
lifted it up as a means of scratching its back. With no weight on it they were
able to move the legs several metres rotating the winch itself at the same
time! With Andy and Mike at the bottom a steady stream of debris, rocks and
clatch, came out. A half hour lunch break was an opportunity to take one of Mike’s
batteries back for recharging. Continued after lunch using my batteries before
finally going to get the newly charged one to finish off the day. One mix of
cement done in the morning session and a second mix in the afternoon one. Depth
now 10.2m. 5 hours of work. John.
Friday, 15 April 2022
Friday 15th April 2022
John Cooper and Andrew Thompson. Started with 1 mix of cement which
was used cementing the boulders left from last time. Then hauled some clatch
out. Then a spell breaking up the bigger boulder on the solid wall side. Still
10.1m to bottom. 2 hours. John.
Tuesday, 12 April 2022
Tuesday 12th April 2022
John Cooper and Andrew Thompson. Started by hauling clatch out.
Then 1 mix of cement and a bit of boulder breaking. Depth was 9.8m to top of
talus cone, 10.1m to foot level. Winch bearing died at end of session. 2 hours. John.
Saturday, 9 April 2022
Saturday 9th April 2022
John Cooper joined Mike Kousiounis and Dave Morrison for the last
part of the session (Mark Helmore having already left). Mike was breaking up
rock with plug and feathers when I arrived but soon switched to clearing. Loads
of rock and a bit of clatch hauled up before calling it a day. 1 hour for me. John.
Thursday, 7 April 2022
Thursday 7th April 2022
John Cooper and Andrew Thompson. Plug and feathers used to create
wall building rocks. 2 mixes of cement then used to build wall. There are 4
bags of sand and 1+ bags of cement remaining. 2 hours. John.
Tuesday, 5 April 2022
Tuesday 5th April 2022
John Cooper, Mark Helmore, Dave Morrison and Andrew Thompson. Quite
a bit of clatch removed. Plug and feathers used to break up a few boulders. One
mix of cement used to build wall. Measured depth 9.7m but did fill up the hole
again so probably 9.5m now. 2 hours. John.
Saturday, 2 April 2022
Saturday 2nd April 2022
Mike K, Andy T and Mark H. Removing the large boulder and clatch. Surprised how low we are after John’s sessions. Roof looked very suspect towards Wookey so cemented 2 bags of sand early for support, Chris W joined us and so did John later. 6½ hours. Mike.
John Cooper took over from Mark Helmore for the last cement mix of the day. Others were Mike Kousiounis, Andrew Thompson and Chris Williams. They had been there all day whilst I only joined after I’d finished in Dave Mitchell’s Dig. Mike had removed the big pointy boulder but decided more support was required before proceeding further along. 1 hour for me. John.
Friday, 1 April 2022
Friday 1st April 2022
John Cooper, Dave Morrison, Geoff Newton and Andrew Thompson. Quite
a bit of clatch removed. Spent some time working on the pointy boulder but it
just splintered when drilling the end. Eventually it wouldn’t release a plug
and broke the tip off the drill bit. Dropped the boulder so it is now possible
to drill the top of it. Depth at end of session was 9.4m. 3 hours. John.