Wednesday, 12 February 2025

Wednesday 12th February 2025

Mike Kushy and Sam Hill. MK arrived around 3, took in drill and broke up the last big rocks laying around. Then crowbared the loose blocks at the sharp end, these were then reduced down in size again. Started then to do the usual wall building and chucking slop behind it and of course a bit of prodding. All the buckets were filled and pushed higher up cave. SH arrived around 4.30, he moved the rocks and buckets up into the dam. We had a bit of a play with the hose, oh the dam doesn't leak anymore! After all this we decided to clear out the tunnel from the hauling spot to Tooth Dig. We did these with both of us on the Tooth Dig side and all the spoil was sent to the far side of the approach passage to TD, where there was a handy alcove. Upon clearing we noticed there was quite a bit of space in the floor heading to the recent Dig area. SH went into the dodgy boulder area above the dig face and a close light connection was made (this may be worth opening up). The dig face just keeps going forward, but until the floor is lowered/ceiling is raised it's hard to retrieve any more mud. There a nice vertical gap in the ceiling ahead about 6 inches wide, packed with grit. 5 hours for me, Mike.

MK rodding the mud ahead. Photo SH

Closer view. Photo SH.

The dig face to begin with. Photo MK

Sunday, 9 February 2025

Sunday 9th February 2025

Mike Kushy and Mysti Ommer. A sunny but cold morning. MK got to site around 10 with drill, broke up the last of the bigger rocks at the face. MO arrived around 11. With MK hauling and MO filling buckets the dam was cleared in just over an hour. The pair headed to surface to mix up some cement. 2 buckets mixed and each carried a bucket to the dig site. These were transferred into smaller buckets at the bottom. MK set to work cementing, whilst MO took the buckets and headed out to start another mix. MK then headed to surface. Alex Randall showed up, but we decided not to make yet another mix, MO had to leave. MK took 2 more buckets in and used them on side walls and a bit on the dam. Horrible foggy wet weather on return to surface. 5 hours. Mike.