To watch the diggers in action on YouTube click here
Tuesday 31 October 2023
Tuesday 31st October 2023
Sunday 29 October 2023
Sunday 29th October 2023
Mike Kushy, Dave Morrisom and John Cooper. Mike and Dave clearing out bang spoil. Some of the charge didn't go off for some reason, never mind though as the blocks we want to bang had shifted from the charge that did go off allowing removal. Cleared enough ready for drilling. John joined us at the end. Good draught. 2 1/2 hours. Mike.
Looking into the chamber at the bottom, all seems to be holding up okay. Photo MK. |
The bottom after clearing. Red block wiggles and will come out. Blue
crosses supposed drilling point. Yellow crosses maybe to be drilled,
would be good to get out. Photo MK. |
Sunday 22 October 2023
Sunday 22nd October 2023
John.Cooper and Mike.Kousiounis. Setting charge in holes drilled by John mid week. All went off fine. No sign of any newts in the tunnel. 1 hour. Mike.
Saturday 21 October 2023
Saturday 21st October 2023
Pete Hann, Jude and Adrian Vanderplank, Nigel Graham as surface support.
All down the entrance shaft to firstly look at Johns drilled shot holes, (Very nice!)
Then on down into the original dig, a couple of times there seemed to be a strange grunting noise particularly in the more snug sections, strange?
Pete was impressed with the bedding chambers and thought they could be quite photogenic. We went to both ends, but not the very ends and I missed the way into Tooth dig, and found myself looking at a small bucket and rope and an even smaller hole and thinking if they’ve gone through that I’m seriously impressed. A steady trip out, looking for draughts and anything else which might be of interest. Adrian.
PS from John Cooper. When Pete returned the key he said "Don't ever give me that again!"
Thursday 19 October 2023
Thursday 19th October 2023
John Cooper. Went to drill some holes in the bottom. 6 holes 300 –
500mm deep ready for Mike on Sunday. 1 hour. John.
Wednesday 18 October 2023
Wednesday 18th October 2023
Mike Kushy, John Cooper and Dave Morrison (Tuska). Clearing out bang spoil, clearing the tunnel and bringing the builders ladder out. Some suspect rocks left in place, not sure about pulling the smaller rock out as it had alot of resistance and decided to cement up to provide some support. 2 hours. Good draught. Mike.
Spoil to clear. Photo MK. |
More spoil (looking horizontally). Photo MK. |
After clearing. Photo MK. |
Cement/building work. Photo MK. |
Plan for next stage. Photo MK. |
Sunday 15 October 2023
Sunday 15th October 2023
AM: Mike Kushy and Dave Morrison (Tuska). Banging the holes drilled by John Cooper mid week. Really good holes to widen out the bottom.
PM: Mike Kushy, Tuska and John Cooper. Cleared the debris from the morning. Drilled 6 holes at 900mm then set off.
Debris after 1st bang Photo MK. |
Bottom cleared. Photo MK. |
Tuesday 10 October 2023
Tuesday 10th October 2023
John Cooper. Went to drill some holes in the bottom. However
there was still debris on it so after clearing in into the tunnel and the hole below
drilled the walls instead. 1 hour. John.
Sunday 1 October 2023
Sunday 1st October 2023
Mike Kousiounis and Dave Morrison. Started by clearing the bottom of the shaft. Bucket still snagged in a couple of places so after clearing we opened up the shaft with some more plug and feathering. Happy with the bucket pull, we set about doing some cement work. John Cooper joined us around 2pm and we finished the last bit of cementing that needed doing to fully stabilise the shaft ready for banging. 5 hours. Mike.